Bathroom Renovation: The Right Sequence of Work

Why Sequence Matters

Wrong order means wasted money. Never tile before replacing pipes.

Correct Order

  1. Demolition (1-2 days)
  2. Plumbing & electrical (2-3 days)
  3. Wall/floor leveling (2-3 days + drying)
  4. Waterproofing (1-2 days)
  5. Tiling — walls first, then floor (3-5 days)
  6. Grouting (1 day)
  7. Ceiling (0.5-1 day)
  8. Fixture installation (1-2 days)
  9. Accessories & sealant

Planning a Bathroom Renovation?

Our plumbers handle everything — from pipe replacement to fixture installation.

Need a plumber?

Submit a request and our technician will contact you within 15 minutes. Emergency dispatch from 30 minutes.

Welcome to Saport! 👋

Plumbing without unnecessary calls and waiting

Submit a request online

No need to call — just fill out the form on the website

Technician is nearby

Your request instantly reaches technicians nearby — no operators or queues

Technician will contact you

The person who will do the work — directly. Fast, without intermediaries

Automation = low prices. No call center or commissions — you pay only for the work.

Submit Request

Warranty on work up to 3 years